1 Please place professional isolation facilities before installation for ensuring the safety of workers.
2 The road surface should be level and even ,any repair to the surface should be conducted prior to installation.
3 Boring a specific size hole at the placement location of the road stud that should be Ø140mm*55mm.
4 Ensure the hole is cleaned of all debris.
5 Use a blowtorch to dry any dampness from the holes,failure to do so may result in the adhesive glue not bonding correctly.
6 Pour the adhesive glue into the hole and locate the road stud so that its lighted side is facing towards to drivers.
7 Inspect studs 0.5 hours after installation and re-adjust if there has any movement.
8 Inspect after 4 hours and check that all studs are firmly located and show no signs of movement, if all have set correctly re-instate power.